set up Roof-top Solar PV Power Plant

To set up Roof-top Solar PV Power Plants required documents:- (1) Details of Roof Area, with location / site for setting up Roof-top Solar PV Power Plants. It includes lease agreement, copy of building ownership, etc. (2) Estimated project cost, with detailed break-up; (3) (a) Application / BoM duly signed by the Officer of the project; (b) Application / BoM duly certified by the Chartered Engineer (4) Detailed Project Report (DPR) (5) Copy of EPC Contract or Agreement (6) Single Line Diagram (SLD)/ Detailed Drawings with justification of requirement of cable; Module mounting structures, Inverter, etc. (7) One Affidavit in the MNRE prescribed format The Bill of Material (BOM) shall be submitted to MNRE online. In case, the project developer or organization has received capital subsidy for setting up a Roof-top Solar PV Power Plant, they will furnish copy of the approval letter sanctioning subsidy for that plant.