Rooftop Net Metering in India

Grid Connected SPV Rooftop Systems
Policy and Regulatory Framework in Various States
(As on 14.11.2014)
Sl.
No.
State (Issuing
Authorities)
Solar
Rooftop
Target
Metering
Mechanism
Present Solar
Tariff (Rs.)
Policy/ Tariff *
Validity
Capping of
System Capacity/ generation
EligibilityIncentivesRemarks
1Karnataka
(Govt. of Karnataka & KERC)
400 MW
by 2018
Net  metering
(excess electricity to
be billed as per solar
tariff)
Rs.9.56
(without subsidy),
Rs.7.20 (with subsidy)
01.04.2013 upto
31.03.2018
Not mentionedAll consumersWheeling,
Banking and cross subsidy
surcharge exempted for 10
years
2West Bengal
(Govt. of West
Bengal & WBERC)
34 MW by
2018
Net meteringConsumer
tariff as applicable for
net energy supply
Projects
commissioned till
2015-16
Injection not
more than 90%
of the consumption
from the
licensee’s supply in a year.
All consumersWheeling,
Banking and cross subsidy
surcharge as applicable
3Chhattisgarh
(Govt. of Chhattisgarh & CSERC)
500-1000
MW by
March
2017
Net metering
(excess electricity to be billed @)
50% of the solar tariff)
Rs. 4.35/ kWh2012-2017Injection not
more than 49%
of the annual net generation.
50kWp  to
1 MWp capacity
Wheeling,
Banking and cross subsidy
surcharge
exempted. VAT exempted on equipment’s/ materials.
4Tamil Nadu
(Govt. of Tamil
Nadu & TNERC))
350 MW
by 2015
Net meteringRs.7.01/kWh
(without AD), Rs.6.27/kWh (with AD)
2014-15Capped
commercially at
90% of the electricity
consumption at
the end of the settlement
period.
Excess energy generated beyond the 90% cap shall be treated as
lapsed.
All consumersFor domestic
consumers subsidy of Rs.
20, 000 per kW for 1 kWp system is
provided.
Wheeling, Banking and cross subsidy surcharge as applicable. Electricity tax is exempted.
Mandatory
for all new Govt./local body buildings. For
existing buildings installation in a
phased manner
5KeralaNot
specified
Net meteringConsumer
tariff as applicable for
net energy supply.
Excess electricity to
be billed as per average
pool purchase cost.
From 25.11.2013
until further orders
Capacity shall
be in conformity with the
provisions relating to the
connected load or contract
demand permissible at
each voltage level as specified in the
Kerala
Electricity
Supply Code,
2014.
Not specifiedWheeling,
Banking, open access surcharge
exempted. Exemption from
electricity duty.
(Govt. of Kerala & KERC)
6Gujarat
(Govt. of Gujarat & GERC)
30 MW in
6 cities
Feed-in tariffRs.9.63/kWh
(with AD),
Rs.10.76/kWh
(without AD)
2014-15Not mentionedAll consumersExemption from
wheeling, banking and cross subsidy surcharge.
7Delhi
(DERC order)
Not
specified
Net meteringConsumer
tariff as applicable for
net energy supply.
Excess electricity to be billed as
per average pool purchase
cost.
APPC for 2014-15
and as per subsequent
amendments
Capacity will be
above 1 kWp and as per
sanctioned load. For above
sanctioned load service line cum development
charges to be paid.
All consumersExemption from
wheeling, banking, cross
subsidy and other charges
for a period of 5 years
8Andhra PradeshNot
specified
Net meteringConsumer
tariff as applicable for net energy supply. Excess electricity to be billed as per average
pool purchase cost for a
period of 7 years.
APPC for 2014-15
and as per subsequent amendments
Capped
commercially at
100% of the electricity
consumption in
a billing month.
All 3 phase
service consumers
State’s 20%
subsidy for system up to 3 kWp in domestic sector only.
Exemption from wheeling, banking and cross subsidy surcharge. No charge for open access for third party sale. Electricity duty exemption,
VAT refund.
(Govt. of Andhra
Pradesh & APERC)
9Haryana
(Govt. of Haryana)
50 MW
till 2017
Net meteringConsumer
tariff as applicable for
net energy
supply.  No payment for excess electricity
2014-15Not specifiedAll consumers10%  state
subsidy in addition to 30%
MNRE subsidy,
exemption from external development charges,
scrutiny fee and infrastructure
development
charges, no application and processing fee
HERC
order under
issue
Mandatory
5% for connected
load upto
1000 kWp for all consumers including residential houses on
a plot size of 500 sq.
yard and
above.
10Rajasthan
(Govt. of
Rajasthan)
Not
specified
Net meteringRs.7.50/kWh
(without AD), Rs.6.63/kWh (with AD)
2014-2016Not specifiedAll
consumer(s) of the DISCOMs
Incentives
available to industrial units under Rajasthan Investment Promotional Scheme available to industrial solar power projects, Banking will be allowed
RERC
regulatory orders yet to be issued.
11Uttarakhand
(Govt. of Uttarakhand & UERC)
5 MW per
year
(2013-
2015)
Net meteringConsumer
tariff as applicable for net energy supply. Excess electricity to be billed @ Rs.9.20/kWh
(with subsidy)
2013-2018Not specifiedAll consumersNo transmission
and wheeling charges
12Uttar Pradesh
(Govt. of Uttar
Pradesh)
20 MW
(by 2016-
17)
Net meteringConsumer
tariff as applicable for
net energy
supply.
2016-2017Not specifiedAll consumersState funds for
technical assessment and
deployment of
rooftop SPV on government owned/Public Institutions
At least
25% of available
plinth area
to be utilized for rooftop. UPERC regulatory orders yet to be issued.
13Punjab
(Govt. of Punjab)
Not
specified
Net meteringConsumer
tariff as applicable for net energy supply
2014-2022Maximum
capacity upto
80% of the sanctioned/conn
ected load with
minimum capacity of
1kWp.
All consumersExemption from
wheeling, banking and cross subsidy surcharge. No charge for open access for third party sale.
PERC
Regulatory order yet
to be issued.
*Tariff in every States may change as per orders issued by respective regulatory commissions from time to time.

Popular posts from this blog

Solar energy consulting & management services, detailed project report, energy management consultants, 1 Kw Rooftop Solar System should be for every house

1kw solar power plant specification

MANPOWER REQUIREMENTS FOR SOLAR PV DEVELOPMENT

Industrial Vocational Training for Engineering Students

বিপর্যয় এড়াতে ভূগর্ভের জলস্তর রক্ষা করার ডাক

Solar Energy Industry in India & Its Future Prospects

NIESBUD Entrepreneurship Development Program on Solar Energy

Sustainable Community Development